The Board received a further presentation from Ross Hughes regarding the current position of the development of the new Sports and Leisure Centre.
Ross advised that the project had entered the full planning phase, with a committee decision expected in early September. The design had progressed to detailed stages, with work ongoing to keep the project within budget and aligned with community needs.
It was noted that renewable energy features had been incorporated, including air source heat pumps and solar panels, aiming for a 30% reduction in electricity costs compared to current facilities. Early works related to infrastructure were scheduled to begin soon.
The Chair thanked Ross for his update.