Decision Maker: Executive (up to May 2024)
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
The Executive considered a report that provided an update on the Council’s 2018/19 and 2019/20 Capital Programme, and sought approval for revisions to the General Fund and Housing Revenue Account Capital Programme.
In response to a query raised by the Leader, the Assistant Director (Finance & Estates) undertook to provide Executive Members with clarification regarding the Boiler upgrade/replacement schemes for St. Nicholas Community Centre and Springfield House.
It was RESOLVED:
1. That the 2018/19 General Fund capital programme net decrease in expenditure of £798,260 is approved, as summarised in Paragraph 4.1.1 of the report.
2. That the virement from the deferred works Budget of £49,000 and for the Multi-Storey Car Park of £12,140, as summarised in Paragraphs 4.1.5 and 4.1.6 of the report, is approved.
3. That the General Fund re-profiling of capital expenditure to 2019/20 of £1,627,500, as summarised in Table One of the report, is approved.
4. That it be noted that there is no increase in the capital expenditure for the 2019/20 Housing Revenue Account, as summarised in Table Two of the report.
Reason for Decision: As contained in the report.
Other Options considered: As contained in the report.
Publication date: 05/09/2018
Date of decision: 05/09/2018
Decided at meeting: 05/09/2018 - Executive (up to May 2024)