BALANCING THE BUDGET GENERAL FUND 2027/28

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Cabinet received a report updating Members on the Balancing the Budget priority and the 2027/28 onwards options that met the required General Fund requirement.

 

Members were advised of the updated medium-term financial projections, including increased inflationary pressures and a projected draw on balances to support Local Government Reorganisation.  It was noted that additional savings targets were proposed to reduce future reliance on reserves, and that the draft budget would be presented to Cabinet in January 2027.

 

The Strategic Director and Chief Financial Officer advised that the Council's financial position had improved, enabling additional investment in priorities such as fly-tipping enforcement and woodland management.  She stated that future savings requirements would be significantly lower than in previous years. 

 

It was RESOLVED:

 

1.    That the Balancing the Budget options as set out in the report and Appendix A, totalling £609,417 (saving) for the General Fund 2027/28 (and £20,942 for the HRA) be approved and incorporated into the Council’s budget setting processes.

 

2.    That the inflation and budget pressures as set out in section 4.1 of the report be noted and the £5,000 budget per annum for defibrillators repair and maintenance be approved.

 

3.    That the proposed approach for Local Government Reform (LGR) funding as set out in paragraphs 4.1.4-4.1.5 be approved.

 

4.    That the 2027/28 changes to the administration of Council Tax as set out in paragraph 4.2.8 be noted.

 

5.    That it be noted that the future revision of the Council’s Council Tax Support (CTS) scheme will be dependent on the Governments timeline for LGR as set out in paragraphs 4.2.6-4.2.9.

 

6.    That the use of the Hertfordshire Business rates pooling gains of £107K as set out in paragraphs 4.3.7-4.3.8 of the report be approved.

 

7.    That the completion of the Business rates pro-forma for 2027/28 (NDR 1) be delegated to the Strategic Director (S151) after consultation with the Resources and Performance Portfolio holder (paragraph 4.3.6 refers).

 

8.    That the growth options as set out in the report and Appendix B totalling £296,683 for the General Fund 2027/28 (and £20,942 for the HRA) be approved and incorporated into the Council’s budget setting processes.

 

9.    That it be noted that the future savings target in the main can be met from Fees and Charges as set out in paragraph 4.7.6 of the report.

 

10.That the revised GF MTFS financial summary, as shown in section 4.9 to this report be noted.

 

11.That the Equalities Impact Assessment for the Savings and Growth options (Appendix C) be noted.

 

12.That the Council’s recognised unions be consulted regarding the proposed budget package.

 

13.That key partners and other stakeholders be consulted, and their views considered as part of the 2027/28 budget setting process.

 

 