Decision details

URGENT PART 1 BUSINESS

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Leader firstly reminded Cabinet that the then Executive in July 2023 had agreed to extend the conditional phase of the SG1 Development and start the process of forming a Joint Venture to bring forward the ‘Plot A’ site of the former Swingate House. 

 

The Leader was then pleased to report to Cabinet the positive news that the negotiations had completed and both organisations had signed legal documents to allow works to begin on the site in early October 2024. 

 

Members were advised that the build would take approximately two and a half to three years to complete with residents moving into the homes from 2026. 

 

It was noted that the Swingate Car park would be closed from 7th October for the duration of construction.  In response to a question, it was advised that the Council would be working with season ticket holders and Everyone Active to highlight alternative parking facilties nearby.  Officers would also be asked to ensure there was a clearly signposted disabled access through to the Gordon Craig Theatre.

 

It was RESOLVED that the update be noted.

Publication date: 19/09/2024

Date of decision: 18/09/2024

Decided at meeting: 18/09/2024 - Cabinet