Decision details

STEVENAGE RAIL STATION SERVICE UPDATE

Decision Maker: Environment & Economy Select Committee

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decision:

The Govia Thameslink Railway (GTR) and Network Rail representatives gave a presentation on performance statistics, enhanced services (including the summer timetable), proposals for the future, and the plans for the Stevenage Turnback Facility.

 

During the course of the presentation, the following issues were considered:

 

·           The Cambridge Rail User Group had engaged effectively with Network Rail and GTR over network/timetabling issues; Network Rail / GTR had arranged two meetings with the Stevenage Rail User Group, but unfortunately the Group had cancelled on both occasions.

·           Pocket size fold out timetables would be produced, but there were no plans to produce timetable booklets.

·           The regrettable problems experienced following the introduction of the May 2018 timetable had largely been addressed, including the issue of driver training and operatives being in the right place at the right times.

·           The GTR representatives would respond to Members of the Committee regarding a query raised in respect of the 82% Public Performance Measure relating to the percentage of trains which had run to schedule.

·           With particular reference to Finsbury Park station, the Network Rail/GTR representatives acknowledged the difficulties caused by last minute platform changes.  They explained the reasons for such changes, and would be working to improve communications so that the process in future was much slicker.

·           The Select Committee was advised of ticketing promotions, such as Key Go / Key Card / Oyster Card, together with the possibilities for extending the use of these forms of ticketing.

·           It was noted that the King’s Cross Signalling facility was over 40 years old, and that plans were in progress for the remodelling of this facility, which would entail disruptive weekend works from late June 2019, with peak disruption from December 2020 to March 2021.

·           In terms of the works relating to the Stevenage Turnback facility, the GTR representatives undertook to respond to Select Committee Members on the possibility for the replacement buses to be adapted to take full size bicycles, and possible discounted fares for those using replacement buses during the construction works, and to clarify the situation with regard to the use of replacement buses during weekends throughout that period.

 

It was RESOLVED:

 

1.         That, notwithstanding the absence of representatives from the Stevenage Rail User Group, the developments in the timetabling of trains be noted, and it be hoped that Network Rail and Govia Thameslink Railway’s continue consultation with users and SBC Members over future timetabling development.

 

2.         That Network Rail’s plans for the Stevenage Turnback Facility (5th Platform), including the temporary replacement bus services whilst works take place and the escalated plans for completion of the project, be noted.

 

3.         That the Select Committee continue to take note of events and outcomes relating to GTR timetabling issues and the Stevenage Turnback Facility.

 

4.         That the GTR representatives provide responses for circulation to Select Committee Members in respect of the following outstanding issues:

 

·      Public Performance Measure (PPM) Targets and actual performance;

 

·      Buses – possible adaptation to take full size bicycles;

 

·      Fares – possible discounted fares for those using replacement buses during the construction works on the Stevenage Turnback Facility; and

 

·      Clarity with regard to the situation with the use of replacement buses throughout the construction works on the Turnback Facility.

Publication date: 28/02/2019

Date of decision: 28/02/2019

Decided at meeting: 28/02/2019 - Environment & Economy Select Committee